Missouri’s largest wind farm still largely inactive months after turbines collapse


This recording was made using enhanced software.

Full story

  • Missouri’s largest wind farm has operated at limited capacity for over four months due to turbine collapse investigations. Three turbines fell last year, prompting precautionary measures from the facility’s owner, utility company Ameren, and the manufacturer of the turbines, Vestas.
  • The failures were linked to blade detachments, causing imbalances in the turbines, which led to the collapses.
  • Most of the 175 turbines remain shut down, with no confirmed timeline for full reactivation.

Full Story

Missouri’s largest wind farm, the High Prairie Renewable Energy Center, has been operating at limited capacity for over four months as investigations continue into multiple turbine collapses. The 400-megawatt facility, owned by utility company Ameren, has the potential to power approximately 120,000 homes. However, officials significantly reduced operations after three wind turbines fell to the ground last year.

Why did these turbines collapse?

Danish manufacturer Vestas created the turbines involved. According to Ameren’s director of renewable operations, David Meiners, the failures were linked to blade detachments, which led to an imbalance that caused the turbines to collapse.

QR code for SAN app download

Download the SAN app today to stay up-to-date with Unbiased. Straight Facts™.

Point phone camera here

In response, Ameren and Vestas have implemented precautionary measures. These measures include shutting down most of the site’s 175 turbines while the investigation remains ongoing.

As of March 3, the company restarted about 15 unaffected turbines. However, local officials indicated the number of blade replacements required to restore full operations remains uncertain.

“We’ve been reaching out to Ameren to see what was going on for the plan for the wind farm,” local county presiding Commissioner Mark Shahan said. “We heard several rumors and we’ve reached out to them to say you know you have a plan, so basically it’s a pretty broad plan right now. It’s not precise but they are going to replace turbine blades based on data from inspections.”

What happens next?

Vestas has stated that no injuries resulted from the incidents and that the company remains committed to restoring operations safely. For now, the majority of the turbines remain inactive, with no confirmed timeline for full reactivation.

Ian Kennedy (Video Editor) and Ali Caldwell (Graphics) contributed to this report.
Tags: , , , ,

SAN provides
Unbiased. Straight Facts.

Don’t just take our word for it.


Certified balanced reporting

According to media bias experts at AllSides

AllSides Certified Balanced May 2025

Transparent and credible

Awarded a perfect reliability rating from NewsGuard

100/100

Welcome back to trustworthy journalism.

Find out more

SAN provides
Unbiased. Straight Facts.

Don’t just take our word for it.


Certified balanced reporting

According to media bias experts at AllSides

AllSides Certified Balanced May 2025

Transparent and credible

Awarded a perfect reliability rating from NewsGuard

100/100

Welcome back to trustworthy journalism.

Find out more

Daily Newsletter

Start your day with fact-based news

Start your day with fact-based news

Learn more about our emails. Unsubscribe anytime.

By entering your email, you agree to the Terms and Conditions and acknowledge the Privacy Policy.