Skip to main content
Energy

New Jersey offshore wind farm faces delay due to turbine supply issues

Share

The planned Leading Light Wind offshore wind farm, off the coast of New Jersey, has hit a monthslong delay due to challenges in securing turbine blades. The project, set to be located 40 miles off Long Beach Island and comprising up to 100 wind turbines, is expected to generate enough electricity to power approximately one million homes.

However, Invenergy, the power company behind the development, requested earlier in September that the New Jersey Board of Public Utilities pause the project until late December. The delay comes as the company struggles to secure turbine blades from three different suppliers.

“We are committed in New Jersey to our offshore wind goals,” Christine Guhl-Sadovy, president of the utilities board, said. “This action will allow Invenergy to find a suitable wind turbine supplier. We look forward to delivering on the project that will help grow our clean energy workforce and contribute to clean energy generation for the state.”

QR code for SAN app download

Download the SAN app today to stay up-to-date with Unbiased. Straight Facts™.

Point phone camera here

GE Vernova, the project’s initial supplier, has experienced multiple incidents this year involving turbine blade failures, with debris spilling into the ocean both in the U.S. and internationally.

The manufacturer ultimately informed Leading Light Wind developers just three weeks after the project’s approval that it would no longer build the specific turbine type required.

Turbines from the company Vestas had been considered as a substitute, but were later deemed unsuitable for the project’s needs. Meanwhile, Siemens Gamesa Renewable Energy, the last available supplier, has significantly raised the cost of its turbines, adding another hurdle to the project’s progress.

Invenergy stated that the pause would give them more time to coordinate with supply chain partners to acquire the necessary materials while continuing to advance other development activities during the delay.

This setback is the latest in a series of challenges for New Jersey’s offshore wind ambitions. Last year, two projects from wind energy giant Ørsted were canceled due to rising costs.

Tags: , , , ,

JACK ALYMER: A PLANNED OFFSHORE WIND FARM IN NEW JERSEY IS FACING A MONTHS-LONG DELAY BECAUSE DEVELOPERS ARE STRUGGLING TO FIND TURBINE BLADES.

 

THE PROJECT – DUBBED LEADING LIGHT WIND – IS SET TO BE BUILT 40 MILES OFF THE COAST OF LONG BEACH ISLAND-

AND WILL CONSIST OF UP TO 100 WIND TURBINES-

ENOUGH TO PROVIDE ELECTRICITY FOR ABOUT A MILLION HOMES.

 

BUT POWER COMPANY INVENERGY WAS FORCED TO ASK THE STATE’S BOARD OF PUBLIC UTILITIES EARLIER THIS MONTH TO PAUSE DEVELOPMENT THROUGH LATE DECEMBER-

A REQUEST THAT HAS NOW BEEN GRANTED AMID PROBLEMS WITH THREE DIFFERENT TURBINE SUPPLIERS.

 

GE VERNOVA WAS THE PROJECT’S FIRST CHOICE-

THE SAME MANUFACTURER WHO HAS SEEN MULTIPLE INCIDENTS THIS YEAR OF THEIR TURBINE BLADES FAILING AND SPILLING DEBRIS INTO THE OCEAN BOTH IN THE U.S. AND ABROAD.

 

ULTIMATELY THOUGH, GE VERNOVA TOLD DEVELOPERS JUST THREE WEEKS AFTER THE PROJECT WAS APPROVED THAT IT WOULD NOT MANUFACTURE THE TYPE OF TURBINE THEY WANTED TO USE.

 

THEN A SUBSTITUTE MADE BY THE COMPANY VESTAS WAS DEEMED UNSUITABLE FOR THE PROJECT-

 

AND THE LONE REMAINING MANUFACTURER – SIEMENS GAMESA RENEWABLE ENERGY – SAID IT WAS SUBSTANTIALLY INCREASING THE COST OF ITS TURBINE OFFERING.

 

INVENERGY SAYS PAUSING THE PROJECT WILL ALLOW THEM MORE TIME TO COORDINATE WITH SUPPLY CHAIN PARTNERS TO ACQUIRE THE NECESSARY MATERIALS-

AND THEY WILL CONTINUE TO ADVANCE DEVELOPMENT ACTIVITIES IN THE MEANTIME.

 

HOWEVER, THIS DELAY MARKS ANOTHER SETBACK FOR NEW JERSEY’S OFFSHORE WIND EFFORTS-

FOLLOWING TWO SCRAPPED PROJECTS LAST YEAR FROM WIND ENERGY GIANT ORSTED DUE TO RISING COSTS.

 

TO GET MORE STORIES ABOUT THE U.S. OFFSHORE WIND INDUSTRY – DOWNLOAD THE STRAIGHT ARROW NEWS APP AND SIGN UP FOR ALERTS FROM ME – JACK AYLMER.